Agenda Item #41 Title ACCEPTANCE OF SUBSTANTIAL COMPLETION FOR THE OAK PARK SCHOOL: HVAC RENOVATION - PHASES 11, 12 & 13 PROJECT Description This is the last three (3) of thirteen (13) phases of the project to achieve completion. The architect has prepared the Certificate of Substantial Completion and the final punch list. These phases are the last three (3) phases of contract and are substantially complete in accordance with the contract documents. A copy of the final punch list is available for review at the Construction Services Department. Recommendation That the work performed by Willis A. Smith Construction, Inc. for the Oak Park School: HVAC Renovation - Phases 11, 12 and 13 project be accepted as substantially complete as of 8/1/2008. Contact LEMPE & COLLINS Financial Impact N/A Attachment: BAIenc10-7-08OakParkHVACPh11-12-13SC.pdf |